SR-215/74 Interchange Improvement Project


Project Details:
- Original contract duration: 24 Months
- Final contract duration & explanation of variance: In progress
- Original contract budget: $13.5M
- Changes to final contract total cost & explanation of variance: (Contract is in progress)
- Major issues/problems & how they were resolved: Encountering rocks/manmade buried objects obstructing construction of last two CIDH piles (2.0′ dia). Reviewing other options with the designer to shift both piles away from the obstruction area and maintain same design demand criteria.
Status:
Completed, No Claims, within Budget and On Time.Construction Cost:
$29M